office
remodel
34,198 sq feet
Travelers will be moving their offices and downsizing from downtown Spokane (79,800 sf) to Spokane Valley (34,200 sf).
Scope of work to include selective demolition and build-out of new space, including salvaging and reusing doors/frames, light fixtures, and acoustical ceilings to the greatest extend possible. We will salvage and recycle the existing carpet tile and install new carpet material provided by the owner. Upon completion of the tenant improvements, we will decommission and final clean their existing space downtown.
Tenant improvements at the new site will be substantially complete in mid-January 2024 with approximately 2 months of owner subcontractor work ahead of their first day in the new space on March 4, 2024. The final decommissioning activities will take another month with all contract work complete by March 31, 2024.